In re Appeal of Van Nostrand (2007-229)
2008 VT 77
[Filed 2-Jun-2008]
|
ENTRY ORDER |
|
2008 VT 77 |
|
|
|
In re Appeal of Van Nostrand and Van Nostrand ROW Application #2005-03 |
} } |
APPEALED FROM: |
|
|
} |
|
|
|
} |
|
|
|
} |
|
|
} } |
101-5-05 Vtec |
|
|
|
} |
|
|
|
|
Trial Judge: Thomas S. Durkin |
In the above-entitled cause, the Clerk will enter:
¶ 1.
Linda Nordlund appeals from a judgment of the
¶ 2.
This is the second appeal arising out of a dispute between adjoining
landowners. Nordlund v. Van Nostrand, No. 2007-027 (Aug. 17, 2007) (unreported mem.) sets forth many of the underlying facts, which we
summarize as follows. The Van Nostrands own two
lots on the westerly side of
¶ 3. In April 2000, the Van Nostrands’ predecessors-in-interest, the Kycias, applied for and received a permit from the town to subdivide the front and back parcels. The permit application is not a part of the record. The permit itself consists of a pre-printed, one-page form labeled “zoning permit” that includes a checked box indicating the “permit type” as “subdivision,” a hand-written description of the permitted work as “single-lot subdivision,” and conditions calling for a “revised plat record and/or warranty deed” to be filed in the Town land records.[1] Although § 502 of the town’s zoning regulations then in effect prohibited “land development” on lots that lacked either road frontage or a “permanent easement or right-of-way at least twenty (20) feet in width,” the permit makes no reference to this zoning requirement and contains no findings concerning the nature, width, accessibility, or safety of the right-of-way across the Nordlund property. No appeal was taken from the issuance of the 2000 permit.
¶ 4.
In May 2000, the Kycias conveyed the front and
back parcels in separate deeds to the Van Nostrands,
and in April 2004, the Van Nostrands applied for
permits to construct a four-bedroom, single-family residence and supporting
septic system on the back parcel. The zoning administrator issued the
permits, but Nordlund appealed the decision to the
Development Review Board (DRB). Following a hearing in October 2004, the
DRB voted to reverse the issuance of the permits, citing § 502 of the zoning
regulations, which had been amended in 2002 to increase the width of the
required right-of-way to fifty feet. The Van Nostrands
appealed the DRB ruling to the
¶ 5. In January 2006, the court issued a written decision on the parties’ cross-motions for summary judgment. At the outset, the court observed that issuance of the subdivision permit to the Van Nostrands’ predecessors-in-interest in 2000 clearly did not create a vested right to obtain a zoning permit under the regulations in effect when the permit was granted. See In re Taft Corners Assocs., Inc., 171 Vt. 135, 144, 758 A.2d 804, 811 (2000) (holding that “the balance of competing interests [militate] against giving holders of subdivision permits vested rights to zoning permits under the zoning ordinance applicable when the subdivision permit was sought or obtained”). The court went on, however, to conclude that the back parcel “became a [legal] pre-existing non-conforming lot” in 2002 when the Town amended § 502 to require a right-of-way of no less than 50 feet because the “right-of-way width was deemed in compliance with the zoning regulations [then in effect] when its subdivision was approved” in 2000.
¶ 6.
Thus, contrary to the conclusion of the DRB, the court determined that
the Van Nostrands were not required to demonstrate
compliance with § 502, because that issue had been implicitly resolved when the
subdivision permit issued. The only question that remained, in the
court’s view, was whether the proposed development of the back parcel would “ ‘increase’ the non-conformity of the right-of-way,”
resulting in a narrowing of the road. See In re Miserocchi,
170
¶ 7. Subsequent to the court’s ruling, but before the scheduled evidentiary hearing, Nordlund filed a quiet-title action in the superior court seeking to invalidate the claimed right-of-way across her property. In December 2006, the superior court ruled that the right-of-way was valid and that its width across the Nordlund property was eighteen feet. Nordlund appealed, and we affirmed the judgment. See Nordlund, No. 2007-027, slip op. at 3-4.
¶ 8.
Thereafter, in the pending action before it, the
¶ 9.
We agree with the trial court that this case turns largely on “the
context and relevancy of [the] 2000 subdivision permit.” However, we
disagree with the court’s key conclusion that the right-of-way across the Nordlund property “was deemed in compliance with the zoning
regulations [then in effect] when [the] subdivision was approved” in
2000. It is, of course, axiomatic that, when zoning bylaws are in effect,
“no land development may be undertaken or effected except in conformance with
those bylaws.” 24 V.S.A. § 4446; see In re Kostenblatt,
161
¶ 10. This is not,
however, such a case. To be sure, the trial court’s reasoning—up to a
point—is sound. Consistent with the statutory definition set forth in 24 V.S.A.
§ 4303(10), the town’s zoning regulations define “land development” to include
“the division of a parcel into two or more parcels.”
¶ 11. A subdivision
application, however, implicates an array of associated planning and zoning
issues relating to improvements such as streets, sidewalks, utilities, stormwater-control measures, and access roads.
Indeed, when the subdivision permit at issue here was granted, state
planning law required that municipal subdivision regulations set forth “[s]tandards for the design and layout of streets, curbs,
gutters, street lights, fire hydrants, shade trees, water, sewage and drainage
facilities, public utilities and other necessary public improvements.” 24
V.S.A. § 4413(a)(2).[2] The safety and adequacy of access roads
is a matter of particular significance in the subdivision review process.
As we have observed, “[a] major purpose of modern subdivision regulation is to
locate roads and ensure that they are adequate not only for landowners they
immediately abut but also for others who may pass over them to other
destinations.” In re Shantee
Point, Inc., 174
¶ 12. We have also
recognized that “[t]here is some overlap between zoning and subdivision
regulation because the definition of ‘land development’ for purposes of zoning
regulation includes the division of parcels, the trigger for subdivision
regulation.” In re Tafts Corners, 171
¶ 13. The town here
has not enacted subdivision bylaws and therefore relies on its zoning bylaws
for subdivision regulation. Nothing in those bylaws, however, requires
that subdivision applications meet any standards for safety or adequate street
or utility improvements, and nothing in the record suggests that the planning
commission undertook any such review or applied any such analysis to the 2000
subdivision application, even to determine whether it satisfied the minimal
twenty-foot right-of-way requirement for land development. Indeed, the superior
court’s finding that the “old logging road” in question measured about eighteen
feet suggests, on the contrary, that no such review was undertaken. We
cannot reasonably conclude, therefore, that issuance of the 2000 subdivision
permit implied a conformity with § 502 of the zoning regulations. Hence,
the trial court’s finding that the Nordlund
right-of-way necessarily complied with applicable zoning regulations by virtue
of the subdivision permit was erroneous, and must be reversed. To be
clear, we do not hold that the 2000 subdivision permit is invalid, a result
that would plainly contravene the prohibition against collateral attacks on
zoning permits that have not been appealed. See 24 V.S.A. § 4472(d); City
of
¶ 14. We conclude, in sum, that the trial court incorrectly determined that the Van Nostrands were not required to demonstrate compliance with § 502 of the zoning regulations. Furthermore, inasmuch as it is undisputed that the right-of-way across the Nordlund lot does not exceed eighteen feet in width, it is equally clear that the proposed development cannot satisfy the regulations’ minimum width requirement. Accordingly, the trial court judgment granting the zoning application for construction of a singly-family residence and septic system must be reversed. The trial court did not reach the appeal of the Van Nostrands’ application for a variance from this width requirement, and the case is therefore remanded for this limited purpose.[4]
Reversed and remanded.
|
|
BY THE COURT: |
|
|
|
|
|
|
|
|
Paul L. Reiber, Chief Justice |
|
|
|
|
|
John A. Dooley, Associate Justice |
|
|
|
|
|
Denise R. Johnson, Associate Justice |
|
|
|
|
|
Marilyn S. Skoglund, Associate Justice |
|
|
|
|
|
Brian L. Burgess, Associate Justice |
|
|
|
[1] The permit indicates that it was a “renewal” of an earlier permit issued in 1999, but this earlier permit was not made a part of the record.
[2] This section has since been repealed and replaced by 24 V.S.A. § 4418(1)(B), which contains similar standards and requirements.
[3] Recent legislation had made clear that even towns without specific subdivision bylaws must apply minimal standards to ensure safe and adequate access in reviewing subdivision applications. Thus, 24 V.S.A. § 4412(3) provides:
Land development may be permitted on lots that do not have frontage either on a public road or public waters, provided that access through a permanent easement or right-of-way has been approved in accordance with standards and process specified in the bylaws. This approval shall be pursuant to subdivision bylaws adopted in accordance with section 4418 of this title, or where subdivision bylaws have not been adopted or do not apply, through a process and pursuant to standards defined in bylaws adopted for the purpose of assuring safe and adequate access. Any permanent easement or right-of-way providing access to such a road or waters shall be at least 20 feet in width.
(Emphasis
added.) Section 4418, the successor to § 4413(a)(2), sets forth minimal standards
for towns that choose to adopt subdivision bylaws, and similarly provides that
“[s]tandards in accordance with subdivision 4412(3)
of this title shall be required for lots without frontage on or access to
public roads or public waters.”
[4] We note that there is some evidence in the record to indicate that the Van Nostrands have simultaneously sought approval of a fifty-foot right-of-way that runs exclusively across their own front parcel. Obviously, if they decide to proceed on the basis of this alternative right-of-way, the variance issue may again become moot.